Proppfrexx overlay question

You have a question or need an advice about how to do something? Ask it here!
Post Reply
User avatar
radio42
Site Admin
Posts: 8295
Joined: 05 Apr 2012 16:26
Location: Hamburg, Germany
Contact:
Re: Proppfrexx overlay question

Post by radio42 »

This is may be because you have set the recurrence pattern to every 1 hour.
If you want to run different Overlays for different times of the day, you actually need to define 24 separate Overlays and use the every 1 day as the recurrence pattern.

As an alternative you might also define 24 Program scheduler entries and then use scripts with them, where your first script-line is the TOTH track and you then set the Loop-Line parameter to 2 in order to not repeat this line. This way you don’t even need to define Overlays at all.